Studio Safety Management and Lighting Technology
Classification:
summary description]
In order to ensure the normal production of TV studios, the safety management of studios and the safety of lighting engineering technology have become important factors that cannot be ignored in the safety of live programs and production safety. With the development of economy, the number of TV programs produced in the studio has increased, the production scale has been expanding, and the production cycle has been shortened. At the same time, the atmosphere of the scene also increases the amount of audience input, and this input is often the number of audience and audience passion input.
In order to ensure the normal production of TV studios, the safety management of studios and the safety of lighting engineering technology have become important factors that cannot be ignored in the safety of live programs and production safety. With the development of economy, the number of TV programs produced in the studio has increased, the production scale has been expanding, and the production cycle has been shortened. At the same time, the atmosphere of the scene also increases the amount of audience input, and this input is often the number of audience and audience passion input.
Various forms of program production, the fashionable application of various new materials, the diversity of mechanical and electrical equipment and the investment of high-power computer series lamps, in addition to bringing wonderful and exciting effects to the program and sending gorgeous and emotional appeal to the screen, it also makes the construction and production of the studio program more diverse and complex, which puts forward new requirements and brings new problems to the safety management of the studio and the technical safety of the lighting engineering system.
Studio program production and live, is accompanied by a variety of events that may occur suddenly. In particular, the programs participated by the audience, whether recorded or live, are faced with a large number of audience safety problems, which requires us to do a good job in each specific link carefully.
Because the studio program production has its own particularity, it is often necessary to organize actors, audiences and staff to perform and produce without any protective measures. Therefore, strict construction safety requirements and careful maintenance and management must be carried out for the ceiling equipment layer, lamp boom, scene boom, lifting equipment, lamps, light boxes, stage equipment, driving, curtain, turntable, car platform, lifting platform, sound box, sound box, sound reflection plate, bracket, hanging microphone and auditorium hydraulic mechanical activity platform in the studio. In addition to improving safety measures and rules and regulations, and adhering to the principle of safe operation, we should also pay attention to the safety specification requirements of each (time) installation and dismantling, so as to eliminate potential safety hazards to the maximum extent, so as to ensure the normal production and smooth broadcasting of studio programs. Otherwise, any small omissions, errors, may cause serious, irreparable equipment damage and even personnel injury.
Different stages of 1. prone to accidents
Usually, the safety accidents in the studio mostly occur in three different stages of different nature: installation, program production and live broadcast, and dismantling. With the continuous increase in the production and live broadcast of TV studios, the installation and dismantling of TV stations have become more frequent.
1. Installation
The installation is the beginning of the production of the TV festival (column). Disorderly installation of platforms is like "going to the market": multiple types of work enter the site at the same time, a large number of materials enter the site, and all kinds of equipment are stacked at will; Because the installation time is tight, everyone will rush for time and speed. The equipment layer, overpass, corridor and ground are all staffed. Lights and suspenders are staggered. Although there is a unified command for all kinds of electrical appliances and light box lines, they are still go their own, there is no coordination, communication and humility. These phenomena are serious violations of the rules of operation, ignore the safety requirements, the main source of the accident.
2. Program production and live broadcast process
In the process of program production and live broadcast, due to the aging of lighting control equipment, components and lines are affected with moisture and rat bite, resulting in short circuit, out of control and even electrical fire during the broadcast process. Lack of rationality in scene making process, improper material selection and production, overload hanging of lifting machinery, blocked driving track, hydraulic transmission jam, resulting in loose parts, falling, tilt of props and even scene collapse during the broadcast process; Staff fatigue, carelessness, illegal operation; some unexpected situations also occur from time to time, such as accidentally dumping tea on the control table, causing the mechanical and electrical equipment to lose control, etc., which directly poses a serious threat to the safety of the program and leads to major accidents. Neglecting safety during installation has buried hidden dangers of accidents. A slight negligence during the performance will inevitably cause serious consequences. There have been painful lessons on this point.
3. Dismantling
Teardown is the real end of a show or party. At this time, safety awareness is lifted and safety regulations are ignored. However, accidents often occur at this time. Why? I thought it was time for me to "perform" when the audience was gone and the actors were gone, so I staged an "accident". Mental paralysis, lax spirit; Not according to the rules of operation, barbaric demolition, broken equipment, damage to equipment, smashing personnel often; There are also records of personnel falling and dying. To dismantle the stage is to "untie" the stage ". Safety ropes must be fastened for high-altitude operation, and work ropes must be used to avoid misses and missteps, and to prevent objects from being out of control or thrown down at will. However, some of our staff, even full-time staff, just like "flying trapeze". In addition, if you don't pay attention to and don't clean up the waste derived from the installation and dismantling of the platform in time, of course, it is inevitable that you will be scratched and bumped by other sharp corners such as iron wire, nails, wood ballast, glass fragments, etc.
2. safety management
Safety is not a narrow and simple "fire prevention". Fire prevention is very important, but we can not see the "fire" should be how to prevent? Those easy to cause the hidden dangers of disaster we should be how to eradicate, put an end to? In our daily work, how to find and solve these problems? I am afraid that this is the most important.
The safety management of the studio is multi-level and all-round. The studio is an important "workshop" for the production of TV programs, and it is also a "public place" where TV equipment and personnel are relatively concentrated ". "Public safety" should be the top priority for studio production. Here, I would like to discuss with my friends the production safety of the studio program in addition to the "police security. We also discuss from three different sides.
1, Infrastructure Security Management
For the studio, the infrastructure is all the "original" equipment that provides program production in the studio. In Sichuan TV Station 600 M2 Studio, it includes: structural floor, equipment floor, space equipment below the equipment floor, second-floor corridor, ground equipment and materials, as well as studio lighting control room, studio air conditioning system, studio scene props production room, actor lounge, dressing room, costume room, waiting room and actor pass-through, etc. Safety management in all directions, if there are omissions, will inevitably directly or indirectly affect the studio program production. Therefore, the safety precautions of each link must be cautious and proactive in order to avoid losses and ensure the safety of the studio.
1) The structural layer, as the name implies, is the basic framework for carrying the equipment needed for program production. The self-weight and negative weight of the structural layer are the first and most important for the safety of the studio. The original structure layer we used is steel and wood structure. It has been transformed into an all-steel structure, replaced and removed all wooden equipment, installed a safety net, and improved electromechanical grounding safety protection. Equipped with 1211 fire extinguishers.
2) On the equipment floor, all boom lifting motor systems, boom lifting digital terminal cabinets, lamp adjustment digital terminal cabinets are installed in the studio, and 90% of lighting lamp cables, computer lamp signal lines, color changer signal lines, etc. in the studio are laid. The equipment layer shall be cleaned regularly, and all the waste of iron wire, wooden sticks or other materials discarded after installation and dismantling shall be cleared out of the equipment layer to prevent blocking, blocking the normal operation of other equipment, or causing short circuit of electrical appliances and causing accidents. The equipment shall be cleaned, lubricated and fastened regularly to prevent loosening and falling. In the space above the equipment floor, air-conditioning airflow ducts are erected to adjust the temperature of the high-rise space of the studio. It is forbidden to place any objects on the air-conditioning airflow duct to prevent accidents caused by sliding objects due to duct vibration.
3) The space below the equipment layer is an important performance and bearing area for the atmosphere effect and environmental atmosphere of the evening program in the studio. In this space is equipped with: two sets of movable curtain blue and white, both of which are fireproof and flame retardant curtains; 20 air conditioning vertical downward air supply ducts. In order to balance the studio stage, the audience area space temperature. There are 46 composite horizontal booms, 24 traveling vertical cranes and 12 fixed vertical cranes. More than 340 lamps and lanterns of various types, 100 color changers and other effect transmitters such as cigarette machines and snowflake machines; 2 horizontal scenery poles; One vertical lifting site monitoring screen; 2 sets of ring-shaped curtain tracks; 4 light-chasing hangers, etc.
They are all hanging unobstructed over the actors, audience and crew, as well as over the cameras and TV screens. Any mistake in installation or operation may lead to loss or disaster. Therefore, the inspection, maintenance and management of equipment in this area is particularly important. In addition to regular cleaning, refueling and fastening, detailed inspection should also be done, such as whether the lamp hook is loose, whether the lamp cover is smart, whether the color paper clip is firm, whether the connector is consistent, whether the power cord is aging, whether it is close to the lamp shell, etc. Never take any chances, or the accident will never be undone. As small as a screw, as light as a piece of filter paper, can not let it fall, otherwise, the safety psychological effect of the audience will be tense and disordered, and calm can be restored after a period of time.
4) The corridor on the second floor is an important channel connecting the ground and the equipment layer, and is also an important fire fighting channel. Air-conditioning airflow ducts are provided under the corridor to regulate the temperature of the ground floor space of the studio. There are two secondary power supply transfer distribution direct fire socket cabinets and adjustable socket cabinets at the front and back of the corridor, and 1211 fire extinguishers, etc.
5) The ground is the stage and the auditorium. Due to the "congenital deficiency" of the studio, the materials and equipment are mostly set at two ends, with entrance and exit channels on both sides. The wall is 30 CM from the ground with multiple air conditioning air outlets to adjust the temperature of the bottom space of the studio and the stage and auditorium. The stage is about 200 M2, the auditorium is about 120 M2, the canopy, lights and scenic spots are about 80 M2, the shooting work area is about 60 M2, and other areas are about 140 M2 (including passages, wall cabinets, etc.). Air conditioning airflow ducts are installed in turn in front of the canopy. The canopy floor lamp and other effect lamp trench area; Triangular 6 M upright lamp stand 4 products; TV screen; Stage 200 M2 40 CM above the ground; No.1 and No.3 cameras and rocker camera work areas; Finally, the auditorium hydraulic mechanical movable table with a total height of 3.6 m. Two secondary power supply transfer distribution cabinets are set on the left side behind the canopy. In addition, 1211 fire extinguishers are provided at each work point and at the entrance and exit of the studio.
6) The studio lighting control room is an important power distribution hub for the lighting production of the studio program. The dimming console is the heart of the lighting system. Once a failure occurs, it will definitely affect the program production. Therefore, the lighting control room is the focus of inspection and maintenance.
7) Actors' lounge, dressing room, clothing room, waiting room and actors' pass, etc. On the surface, there is no possibility of safety accidents in these places, but this is not the case at all. Major accidents often happen inadvertently.
Strengthening the safety management of this work and enhancing the awareness of safety management in this area are the prerequisites for preventing the following accidents. It can be said that the infrastructure security management is an important daily work of the television studio, which should be run through our various work links, so that the accident may be executed in the bud. Regular inspection of the safety status of the equipment can find problems in time, so as to formulate methods and processes to solve the problems, put forward feasible guidance, supervision and terms of use, and operate according to correct procedures, methods and rules and regulations.
2. Safe operation on site
Before entering the studio, any department, crew or party of the TV station should contact the studio management department in order to get the corresponding support and cooperation. Both parties shall determine the scope of work responsibilities and arrange the work schedule. In the whole process of all kinds of materials entering the site, loading, lighting, synthesis, rehearsal, recording, live broadcast, dismantling and removal, both parties shall arrange their respective responsible persons to command their respective work scope on the site and be responsible for the safety of the site. At the same time, arrange personnel to carry out safety inspection on their respective systems.
Acts, equipment, appliances, fireworks, open flames, explosive effects, etc. that must be performed but are prohibited in the program should be reported to the competent department in advance, and need to be subject to public security fire inspection, approval, and supervision. For example, the kerosene and rosin used in Sichuan opera "Spit Fire", the candle used in "candlelight effect" and the management of the holding actors, especially the young actors, after lighting.
Consciously strengthening the safety management work before the program production and eliminating the hidden dangers of safety are important factors to ensure the smooth progress of the studio program production and live broadcast. In order to let the entry personnel know the infrastructure status of the studio, the studio staff should also know the drawings and installation profiles of the entry platform, so that both sides can know fairly well and form a tacit understanding of the work.
Mobilization operation, must pay attention to the following issues
1) Keep the entrance and exit channels of the studio unblocked. The staff on duty of the studio shall introduce the working environment of the studio to the installation staff in detail, such as: temporary power distribution box, up and down stairs, matters needing attention in equipment floor work, fire safety equipment location, etc. Those who can move and those who should not move should be clearly marked or notices for the people should be made.
2) Attention must be paid to clearing the floor when installing the platform: the packing boxes shall be stacked according to the designated place; Scenery and props shall be placed in the order of the programs on the stage. Remove the garbage derived from the installation at any time, especially the sharp objects such as iron wire, nails and glass that may pose a threat to personnel and performance equipment after the packaging is disassembled, and remove them in time and properly dispose of them, so as to reduce the probability of "accidental injury. Creating a good working environment is also an important indicator of civilized construction.
3) In the process of installation and dismantling, the necessary portable tools are the main conditions for ensuring self-safety, reducing accidents and safe operation. However, the tools must be included in the waist bag or tool bag, and some tools must be fixed in the bag to prevent slipping out, let alone falling. The weight of lamps and equipment on the boom should be strictly limited to the weight of the rated load. Mechanical equipment shall be controlled to operate within the range of bearing safety factor and operated by full-time personnel. Special hook fixture shall be used for lamps and lanterns, and bolts of all parts shall be locked; safety ropes shall be tied for lamps, color changers, distributors, etc. to ensure that objects do not fall off.
The inspection and maintenance of lamps, lines and plugs must be carried out after the power supply is cut off, and live work should be avoided as much as possible. Regardless of the backbone cable, branch cable, should be neatly arranged. The power cord at the tail of the lamp should not be too long, so that the light does not affect the rotation of the lamp. There should be a certain distance between the cable and the lamp shell, away from the heat source of the lamp shell, and avoid sticking to it. For temporary lamps, lamp stands, effect lamps, smoke machines, consoles, timers, scorers, computer workstations, etc., attention should be paid to maintaining a certain safe distance from the audience. For these temporarily arranged on the ground cable, signal line, etc., the length should be moderate, pay attention to check whether the cable is aging, the outer skin is damaged, where the aging, damaged cable, should be replaced in time. The layout of ground cables should be as neat as possible, straightened and arranged and fixed on the ground with adhesive tape. The surplus cables should also be straightened to avoid heating. If necessary, slope cover plate should be set to prevent damage and accidents.
Before installation, check, test, clean and maintain the equipment, including lamps, bulbs, plugs, reflective bowls, lenses, lenses, etc., so that broken lenses and lenses can be found and replaced, hidden dangers such as leakage of lamps, loose plugs and broken plugs can be eliminated before installation, which can also reduce the inconvenience of climbing for maintenance.
After installing the platform, carefully check the suspended objects such as scenery device, lighting boom, hanging device, etc. to see if the lamps and scenery are hung or collided with each other. If so, they should be eliminated one by one in time. To enhance the awareness of self-protection, high-altitude operations must be equipped with safety ropes; In order to prevent electric shock or wiping, scratching or scalding, cotton gloves should be worn. Should wear soft and flat shoes that are convenient for action, pay attention to whether there are steps drop and stage device obstacles when walking. Special attention should be paid to the safety of the foot when installing and dismantling the platform to prevent the damage of acute corners, edges, wood, iron wire and nails of utensils. The quality of the team is the first choice for installation safety. A skilled operation, sophisticated technology, civilized construction, and familiar with the studio program production requirements of the installation team, they create a win-win situation.
3, coordination and tacit understanding of safety
The simultaneous entry of multiple types of work, or the assembly of multiple types of work in a short period of time, is another feature of the evening installation of theaters, stages and television studios. To complete the scene production, synthesis, rehearsal within the specified time, and perform, produce or broadcast according to the scheduled time, it is difficult to succeed without the spirit of coordination, humility, mutual assistance and cooperation. This spirit of mutual assistance and cooperation is the basis of safe construction (installation and dismantling) and the guarantee of the success of the party.
Coordination is multi-faceted and all-round, involving personnel, time and place. Both horizontally and vertically. Just take the installation of a TV song and dance party as an example. Horizontal: it involves actors, camera, recording center, broadcast control center, logistics, transportation, fire protection, security and other departments; vertical: it involves directors, art designers, scenery, installations, lighting, sound, makeup, clothing, props and other aspects, as well as units, departments, personnel, time, location arrangements, etc. related to various aspects, all these must be coordinated to form a tacit understanding. Moreover, no matter which aspect, it involves personnel safety, equipment and material safety and operation safety.
An evening party is actually a huge technical and artistic engineering system. The performance scene is the production workshop of performing art works. All the personnel in front of and behind the stage are a program manufacturing team that is integrated by the "party" and temporarily organized for the goal of "audience. It is impossible to organize and integrate personnel, materials and equipment from different units, departments and nationalities into works of art recognized by the audience on the TV screen without the spirit of coordination, humility, mutual assistance and cooperation.